Reply from iamravikulkarni on Feb 20 at 3:24 PM I think there is limitation to COHV. you can restrict the data with Production supervisor, date ranges etc. Date ranges should be a good option to split up orders and process.
| | | ---------------Original Message--------------- From: Pugazhendi Subramani Sent: Thursday, February 16, 2017 5:11 AM Subject: Production Order CLSD Status I have 450000 production orders in TECO status. I want to set the CLSD status for those orders by using mass t code COHV. But in this program only four orders completed per hour by background. I want to speed up my activity. Please suggest to do the same. Regards, S . Pugazhendi. | | Reply to this email to post your response. __.____._ | _.____.__ |