RE:[sap-log-pm] Work Order Basic Start Date Changed To Three Year Ahead When It Is Created From Maintenance Plan

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Reply from wagoss56 on Jul 20 at 10:36 PM
Is this a strategy based plan? If so, do you have any offset or subsequent set?

What are your Scheduling parameter settings for your work order configuration (not maintenance plan Scheduling parameters, but work order config)?

---------------Original Message---------------
From: minhaj_ahmed
Sent: Friday, July 14, 2017 9:10 AM
Subject: Work Order Basic Start Date Changed To Three Year Ahead When It Is Created From Maintenance Plan

Hi Team,

When work order is created from maintenance plan basic start date is moved to 2020 year. Actually basic start date should be planned date that is (August 2017) but it is coming as Feb 2020 year. Can you please suggest what will be the reason for this.This happens to same work center maintenance plans only.

Thanks in advance.

Regards,
Minhaj

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
© 2017 Ziff Davis, LLC. and message author.
Ziff Davis, LLC. 28 E 28th Street New York, NY 10016
wagoss56  

Consultant
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Earn Recognition for Your Contributions at Toolbox for IT. Gain Points for Community Achievements

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language