RE:[sap-log-pm] PM Re-Schedule

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Reply from wagoss56 on Jul 20 at 10:51 PM
If you have the Confirmation required box checked, you can not generate a new work order until the previous one is complete. If the box is not checked, you should be able to do a Restart or a Restart in Cycle if it is a Strategy based plan.

If you wanted to change the called work order dates, you should be able to do that, but it won't affect the next set of dates on the plan if your Shift Factors are zero. After the work order is called, you may be able to "Fix" the date from the IP10 schedule.

---------------Original Message---------------
From: Garcia_Destino
Sent: Saturday, July 08, 2017 9:05 AM
Subject: PM Re-Schedule

I have PM already scheduled in SAP the call date is 18/08/2017 and there is a need to shift one Item to 12/07/2017. How can I proceed with this change? I need support from everybody, kindly. I am waiting for your feedback, thanks.

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
© 2017 Ziff Davis, LLC. and message author.
Ziff Davis, LLC. 28 E 28th Street New York, NY 10016
wagoss56  

Consultant
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Have a technical question? Need to find IT solutions? Ask your peers in the Toolbox for IT community.

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language