RE:[sap-log-pp] Subcontracting production order configuration
Posted by
Admin at
|
Share this post:
|
0 Comments
| | Posted by Juan R on Mar 8 at 1:43 PM | |
One remark, document type ZMCD is the purchase requisition that has to be created to create the subcontracting purchase order to acquire the FP from the vendor.
Thanks again.
Juan
---------------Original Message---------------
From: Pablo R
Sent: Monday, March 08, 2010 1:39 PM
Subject: Subcontracting production order configuration
> Hi Experts, I need your help on this issue. I have an scenario where I have a manufacturing process done at a vendor for which I intend to use subcontracting production. The component for this process is supplied from stock. The returned material has a different material code. I have configured the finished product FP (the one built at the vendor) with procurement type F and special procurement type 30 (subcontracting) and the component CO with procurement type E and special procument 20 (external procurement) since it comes from a plant of the same company code (I've also tried setting it to procurement type X to see what happens). I've created a reference operation set Y with a work center X with a control key PP02 (Routing/Ref. op. set - external processing). On the material BOM i've set the component CO with item category L (stock).
>
> When I create the Work Order, as I attempt to chose the reference operation set, I get an error message "Item category L not allowed with document type ZMCD." My question is, is this message talking about the component or the finished product? I cannot get pass this error message.
>
> Thanks for your help.
>
> Juan
__.____._ Thanks again.
Juan
---------------Original Message---------------
From: Pablo R
Sent: Monday, March 08, 2010 1:39 PM
Subject: Subcontracting production order configuration
> Hi Experts, I need your help on this issue. I have an scenario where I have a manufacturing process done at a vendor for which I intend to use subcontracting production. The component for this process is supplied from stock. The returned material has a different material code. I have configured the finished product FP (the one built at the vendor) with procurement type F and special procurement type 30 (subcontracting) and the component CO with procurement type E and special procument 20 (external procurement) since it comes from a plant of the same company code (I've also tried setting it to procurement type X to see what happens). I've created a reference operation set Y with a work center X with a control key PP02 (Routing/Ref. op. set - external processing). On the material BOM i've set the component CO with item category L (stock).
>
> When I create the Work Order, as I attempt to chose the reference operation set, I get an error message "Item category L not allowed with document type ZMCD." My question is, is this message talking about the component or the finished product? I cannot get pass this error message.
>
> Thanks for your help.
>
> Juan
Copyright © 2010 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Related Content
In the Spotlight
White Papers
In the Spotlight
55% of IT Pros Use Social Media to Advance Their Careers. See the Survey Results
View this thread online
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion