Re: [sap-log-pp] PP_MRP_Discontinued Parts and alternative Parts

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Posted by Denise Michaels
on Aug 20 at 3:24 PM
Mark this reply as helpfulMark as helpful
This should be possible using settings in the MM, no need to change the BOM. 
Please verify: both old and new materials are planned via MRP and both have same stockkeeping unit.
--- On Wed, 8/19/09, fgoudarzi via sap-log-pp <sap-log-pp@Groups.ITtoolbox.com> wrote:

From: fgoudarzi via sap-log-pp <sap-log-pp@Groups.ITtoolbox.com>
Subject: [sap-log-pp] PP_MRP_Discontinued Parts and alternative Parts
To: "Denise Michaels" <deniseemichaels@yahoo.com>
Date: Wednesday, August 19, 2009, 11:53 PM


Posted by fgoudarzi (Consultant)
on Aug 20 at 2:54 AM
Hi All,
I have a material, for example, material "A", is to be replaced by another material, that is, "B" in the future. For this reason, in the material master, in MRP4 view, I set Discontin. ind. equal to"1", effective-out date and follow-up material.
When I see requirement/stock list for material "A", I see a row in the name of "effective-out date" and below this row, its requirements. I expect that after effective date no requirements be generated for "A" and instead of that, requirements be generated for "B". But in the requirement/stock list for material "B", there are no requirements, in spite of the fact that available quantity in the effective-out date is under zero.
What should I do
PLZ help me.
__.____._
Copyright © 2009 CEB Toolbox, Inc. and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Denise Michaels