Posted by
Admin at
I need some guidance in trying to analyse the cost for a part A in plant code US03. The part has a BOM that contains 3 kits (3 Phantom assemblies: E-50). Only one phantom assembly P1 has been marked as cost relevant on the BOM for part A. However all 3 phantom assemblies are getting included in the costing for part A. I have checked the individual BOMs for these 3 phantoms and they have all components marked as cost relevant and the BOM status is set to 1. Could this be the reason? Could you please let me know why the other 2 phantom assemblies are included in the costing? | __.____._ Copyright © 2011 Toolbox.com and message author. Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251 | | Popular White Papers In the Spotlight _.____.__ |