Question from vikasgupta_kota on Jul 14 at 4:19 AM Hi Friends, My query is with regards to the Required Start Date field in notification. Scenario is like this: There is a maintenance plan with priority 1 (Very high). I am creating a notification through Maintenance Plan, that means the call object is a notification. When I schedule the maintenance plan, the cycle is 1 month. Current date is 13/07/2017. The first plan date is appearing as 12/08/2017 in IP10. But when I save the call, in the notification the Required Start Date is appearing as 10/08/2017. The call horizon is 0%. Tolerance is also 0%. Why the Reqd Start date is 10/08/2017? As per my understanding, it should be same as Plan date, i.e. 12/08/2017. This is the SPRO setting for priority 1. Prty Pr Pr type Rel str Rel end Priority text SDUn EDUn SM 1 Service Priorities (Blank) 4 Very high H H Thanks in Advance, Vikas | Reply to this email to post your response. __.____._ | _.____.__ |