Question from Jules67 on Aug 11 at 2:54 AM I am working with a refinery and they use SRM for material purchases. However, they have a distinct lack of visibility and are struggling to see availability of materials, planned delivery dates and even which Work Orders the PO's are required for as they also run MRP. I suspect the use of SRM and PM together does not work too well. Does anybody have experience of using SRM with PM (especially refinery based)? Many thanks. | Reply to this email to post your response. __.____._ | _.____.__ |