Reply from Jhie_beluso on Aug 11 at 1:31 AM Hi, Option 1 Use Z4SC type PO to do conversion of SKUs. 541 movement for the old stocks to move the stocks to subcontracting 543 to consume the stocks 101 mvt to receive the 2 stocks in Option 2 Mvt 201 for the stocks to be depleted Mvt 202 for the stocks to be added Hit both in same cost center that it will offset each other. Hope this helps, Jhie
| | | ---------------Original Message--------------- From: Needhelp Sent: Wednesday, August 10, 2016 10:19 AM Subject: How To Transfer A Purchased Assembly To Its Components I have a purchased assembly that is made up of 2 reference components. We need to move the total amount of inventory on the purchased assembly, over to its 2 components. I know I can move 1 material to another, using an 309 movement on MB1B, but is there a way to move 1 material to 2 materials? | | Reply to this email to post your response. __.____._ | _.____.__ |