Reply from Diane S on Jan 9 at 8:29 AM The Answer is yes you do. . Manual ROP requires you to manually calculate what the ROP number should be, and manually update the MM in SAP to that quantity. Automatic ROP does it automatically when you run the forecast. It calculates the ROP quantity based on past use, and automatically updates the MM with that quantity.
| | | ---------------Original Message--------------- From: vijesh vijayan Sent: Wednesday, January 08, 2014 2:39 AM Subject: Automatic Reorder Point Planning for Packaging Hi Team, We are planning to implement reorder point planning for packaging items, kindly let me know the mrp types to be considered for manual and autom. reorder point planning and if we are using autom. reorder point planning, do we need to activate forecasting view? Thanks to advise, Vijesh | | Reply to this email to post your response. __.____._ | _.____.__ |