Hi Rashid, Creating a cost element group is not sufficient. If you are trying to upload through excel file, you need to change the planning layout z1-101 in KP66. Position the cursor before Cost element and click 'New Lead Column' and add Cost center in that. Thanks & regards, Sekhar
| | | ---------------Original Message--------------- From: polked Sent: Wednesday, March 09, 2011 9:10 PM Subject: How can I enter multiple cost center in kp06 planning layout Rashid Create a cost center group of the ones you want to update and enter the group in KP06 rather than a single cost center. Ed Polk | | __.____._ Copyright © 2011 Toolbox.com and message author. Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251 | | Most Popular White Papers In the Spotlight _.____.__ |