Hi,
Try to delete first two steps for the setup matrix:
Predecessor | Successor | Time
None | G1 | 1.0 Hr
None | G2 | 1.5 Hr
System is maybe considering this:
Predecessor | Successor | Time
* | G1 | 1.0 Hr
* | G2 | 1.5 Hr
In this way only the fist order of the PP/DS will take the setup time from the routing/pds.
If you already need the:
None | G1 | 1.0 Hr
None | G2 | 1.5 Hr
You can place that values in the routing and system will use them
Let me know if this works.
Regards,
Ra?l
__.____._

Copyright © 2009 CEB Toolbox, Inc. and message author.

Toolbox.com
4343 N. Scottsdale Road
Suite 280
Scottsdale, AZ 85251

0 comments:

Post a Comment

T r a n s l a t e to your language