U Can Do This By Setting Sampling Plan And Chandeing Dynamin Modification Rule.
--- On Tue, 6/2/09, fastcoder via sap-log-qm <sap-log-qm@Groups.ITtoolbox.com> wrote:
From: fastcoder via sap-log-qm <sap-log-qm@Groups.ITtoolbox.com>
Subject: [sap-log-qm] QM Inspection Points
To: "ANKUSH210" <ankush_dandagwal@yahoo.com>
Date: Tuesday, June 2, 2009, 3:37 AM
Hello Gurus,
I have a production order with a quantity of 1,000. I want to ask the user to inspect 1 piece out of every 10 pieces produced. So eventually he would inspect 100 pieces. But I also would like for him to inspect 1 piece for every shift change and 1 piece for every tooling change and after lunch. Please explain how this can be done?
Thanks,
Tom __.____._
Toolbox.com
4343 N. Scottsdale Road
Suite 280
Scottsdale, AZ 85251
In the Spotlight
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion