Hi,
In MD61, instead of using M as Monthly Format in Planning Horizon -
Planning Period you can use D as Day Format.
Best Regards,
Gelyn
________________________________
From: doriangray via sap-log-pp [mailto:sap-log-pp@Groups.ITtoolbox.com]
Sent: Tuesday, June 16, 2009 1:42 AM
To: IMI ALIPON, Genalyn B.
Subject: [sap-log-pp] Planned Independant Requirement
Hi. In std system, date of monthly PIR starts from 1st of the month.
However I require it to start from 25th of the month. Im using fixed lot
size for the final product and MRP type PD. Can the above requirement be
met using planning calendar
? If so, how? __.____._