Thanks Rluja,
I have tried that option before i.e. no predecessor activity. In that
case the conversion from SNP to PPDS orders gives 0 setup time and after
rescheduling also 0 setup time is taken. I already have a default value
of 2 hrs in the routing/PDS which is not been read.Do you have any idea what heuristic and strategy should be used in PP
run and DS.
Thanks,
Sarvesh Rathore
Supply Chain Management Consultant
________________________________
From: rpluja via sap-apo [mailto:sap-apo@Groups.ITtoolbox.com]Sent: Wednesday, June 03, 2009 9:08 PM
To: Sarvesh Rathore (WT01 - EAS)
Subject: RE:[sap-apo] Sequence Dependent Setup (dynamic setup) using
setup matrix functionality


Hi,Try to delete first two steps for the setup matrix:Predecessor | Successor | TimeNone | G1 | 1.0 HrNone | G2 | 1.5 HrSystem is maybe considering this:Predecessor | Successor | Time* | G1 | 1.0 Hr* | G2 | 1.5 HrIn this way only the fist order of the PP/DS will take the setup time
from the routing/pds.If you already need the:None | G1 | 1.0 HrNone | G2 | 1.5 HrYou can place that values in the routing and system will use themLet me know if this works.Regards,Ra?l
__.____._

Copyright © 2009 CEB Toolbox, Inc. and message author.

Toolbox.com
4343 N. Scottsdale Road
Suite 280
Scottsdale, AZ 85251

0 comments:

Post a Comment

T r a n s l a t e to your language