Reply from Luiz_SantAnna on May 16 at 3:53 PM The default system allows you to configure: A) a single purchase requisition for all component items; B) a single requisition to purchase each component item. Customizing Transaction: OIOE ? Code: Collective REQC by order ????? Code indicating that for all operations processed externally ????? And / or for non-stock components, a request for ????? purchase. ? Dependencies ????? If the user does not set this code, it will be generated for each operation ????? Externally processed and / or for each non-stockable component a ????? Purchase requisition. In addition, it is possible to implement via Abap: A) a single purchase requisition for all component items for EACH OPERATION OF THE ORDER LIST OF THE ORDER. Luiz Antonio Sant'Anna SAP PLM Consultant Email: email@removed
| | | ---------------Original Message--------------- From: Blackfyre Sent: Wednesday, May 03, 2017 2:56 AM Subject: Is It Possible to Generate Different Purchase Orders On a Single Purchase Requisition? We have a Purchase Requisition that was generated through a Plant Maintenance Work Order. This Work Order has several operations that are to be attended by different Suppliers. So in the Purchase Requisition these will be different Line Items (#10, #20, etc). For instance line item #10 will be supplier #1 and line item #20 will be supplier #2. The issue comes in when the buyer is processing the PR wanting to create Purchase Orders (PO). They are unable to create PO to supplier #1 for line item #10, and another PO to supplier #2 for line item #20. They can only create one PO for only one line item within a PR. Is there a way of going around this? Like generating different Purchase Requisitions within a single Work Order or Linking different Purchase Orders to a single Purchase Requisition? | | Reply to this email to post your response. __.____._ | _.____.__ |