Re: [sap-log-pp] One Part Consume Seven Same part Produce

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Reply from JoeCa on Jun 27 at 6:29 PM
Hi,

The explanation is not very detailed. Do you mean that you want to produce 7EA of a product from 1Ea of another product or do you mean that you need 7 different products?
In the first case you just have to create a normal production order. In the second case you have two options:
Use by products by entering the 7 materials codes in the ordr BoM with negative quantities.
Use co-products with related BoM in the master record.


GIUSEPPE CASCELLI



Il Sabato 27 Giugno 2015 18:35, Community_Member email@removed ha scritto:

Question from Vivek on Jun 27 at 12:29 PM Dear Sir,

We need to produce 7 parts from one part and its unit of measure is EA.

So, Please suggest process.



Reply to this email to post your response.

---------------Original Message---------------
From: Vivek
Sent: Saturday, June 27, 2015 12:40 PM
Subject: One Part Consume Seven Same part Produce

Dear Sir,

We need to produce 7 parts from one part and its unit of measure is EA.

So, Please suggest process.

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2015 Ziff Davis, LLC. and message author.
Ziff Davis, LLC. 28 E 28th Street New York, NY 10016
JoeCa  

achievements
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Become a blogger at Toolbox.com and share your expertise with the community. Start today.

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language