We have added search box. Key in SAP issue keyword to search
TopBottom

Announcement: wanna exchange links? contact me at sapchatroom@gmail.com.

RE:[sap-log-mm] MRP not to consider dependent requirements, but independent do.

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Reply from MarkM on Jan 9 at 1:42 PM
Our business scenario requires to generate a sales order/ production order for each item we receive. we are a repair factory and our reparable items are received thru SO.
The problem is that we have another SO for shipping and due this, material requirements are duplicated.
In MM02 tab MRP4 there's a field called MRP dep. requirements (MARC-AHDIS) where one options is "Materials for dependent requirements are not planned". If I select this field will it works? Should I select this field for Finished products only or should I also change in raw material?.
Thanks!

---------------Original Message---------------
From: MarkM
Sent: Monday, January 09, 2012 12:20 PM
Subject: MRP not to consider dependent requirements, but independent do.

How can i set for not considering dependend requirements in MRP and just take independent requirments? I have a lot of sales and production orders that are affecting my MRP result and purchasing quantities

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2012 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
MarkM  
MRO Purchasing Supervisor and SAP MM Champion
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Toolbox.com for iPhone & Android: Ask Questions & Get Answers Anywhere. Download the Free App

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language