RE:[sap-log-pm] Setting Start and End Dates from a Maintenance Plan

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Reply from tomevans866 on Jul 24 at 9:39 AM
wagoss56,

I am unable to think of any configuration to have the dates of a work order be the 1st and last day of the month.
You are successful in setting the Basic Start Date to the 1st of the month and holding it. With this, the compliance report could determine the last day of that month (from the calendar). Then determine the compliance date with the Grace Period table.
I would put all the customization in the report instead of trying to customize the work order dates.

Regards,
TRE

---------------Original Message---------------
From: wagoss56
Sent: Friday, July 14, 2017 1:58 PM
Subject: Setting Start and End Dates from a Maintenance Plan

I have a requirement from my client that wants to have the work order due the first of every month (Key Date, 0% Shift Factor).However, they also want to have the Basic Finish date to fall on the last day of the month for which the Plan is called.,

e.g. Basic Start = 01-Jun-2017, Basic Finish = 30-Jun-2017.
Basic Start = 01-Feb-2017, Basic Finish = 28-Feb-2017.

I can achieve getting the Start Date and End Date to be on the first of the month (Key Date, 0% SF, and Scheduling Parameters to not automatically adjust dates (option 3: Do not adjust Basic dates to order start) and Automatic Scheduling is turned off.

Is there standard configuration to have the dates of a Prev. Maint. work order be defined as the first and last day of the month, e.g. Start Date + (# days in month - 1). If not, has anyone defined any development to make this happen?

Note: They are wanting these dates because their is a compliance report that calculates the actual compliance date by looking at these dates and then looking at "Grace Period" table. The grace period is different for each frequency.

Thanks

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
© 2017 Ziff Davis, LLC. and message author.
Ziff Davis, LLC. 28 E 28th Street New York, NY 10016
tomevans866  

Consultant
achievements
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Become a blogger at Toolbox.com and share your expertise with the community. Start today.

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language