Announcement:
wanna exchange links? contact me at sapchatroom@gmail.com.
Posted by
Admin at
Reply from M42987 on May 26 at 12:07 AM I think you have to check control key in your routing
| | | ---------------Original Message--------------- From: Jian_L Sent: Thursday, May 25, 2017 7:58 PM Subject: SAP Doesn't Schedule Operations In Order Hello, I'm trying to use SAP to schedule the operations in a production order, but I noticed that the earliest start date of the operations aren't in order. For example, operation 40 should come after operation 30, but the earliest start date of operation 40 is before that of operation 30. Thank you, Jian | | Reply to this email to post your response. __.____._ | In the Spotlight Become a blogger at Toolbox.com and share your expertise with the community. Start today. _.____.__ |