Reply from JoeCa on May 25 at 10:00 PM Hi, It might be that your routing is set up with operation overlapping. GIUSEPPE CASCELLI
| | | ---------------Original Message--------------- From: Jian_L Sent: Thursday, May 25, 2017 7:58 PM Subject: SAP Doesn't Schedule Operations In Order Hello, I'm trying to use SAP to schedule the operations in a production order, but I noticed that the earliest start date of the operations aren't in order. For example, operation 40 should come after operation 30, but the earliest start date of operation 40 is before that of operation 30. Thank you, Jian | | Reply to this email to post your response. __.____._ | _.____.__ |