Re: [sap-log-pm] If You Did Not Use the PM Work Order Should It Be Released...?

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Reply from Shivpriye on Jan 5 at 4:08 AM
You can directly close the order by clicking Order >> Functions >> Complete
>> Do Not Execute. There is no need to TECO and then do CLSD.

By the way, if you still want to carry forward the order to next period ->
you can just change the start dates, system will do the posting in the
respective MM period.

---------------Original Message---------------
From: Chelseafc1905
Sent: Thursday, January 05, 2017 3:26 AM
Subject: If You Did Not Use the PM Work Order Should It Be Released...?

Hi,

If the order is not going to be done and not released then you can directly
close the order without taking them through NDNR and TECO.

Regards,
Arun

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
© 2017 Ziff Davis, LLC. and message author.
Ziff Davis, LLC. 28 E 28th Street New York, NY 10016
Shivpriye  

IT/IS Manager
achievements
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Have a technical question? Need to find IT solutions? Ask your peers in the Toolbox for IT community.

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language