Reply from Chelseafc1905 on Jan 5 at 3:23 AM Hi, If the order is not going to be done and not released then you can directly close the order without taking them through NDNR and TECO. Regards, Arun
| | | ---------------Original Message--------------- From: joran Sent: Wednesday, January 04, 2017 9:52 PM Subject: If You Did Not Use the PM Work Order Should It Be Released...? Hi guys, Just want to ask this question regarding PM work orders. If you did not use the work orders for that period does it need to be Released then enter NDNR (Not Done Not Required) then TECO or Just CLSD the work order by going to Order - Functions - Complete - Do not Execute since we are not using the work order. Cheers, Joe Ranola Maintenance Scheduler OneSteelP | | Reply to this email to post your response. __.____._ | _.____.__ |