Reply from jhemp2011 on Jun 8 at 10:29 AM I found the issue. It is resolved. Normally we check fix for the vendor. I noticed that only one can be the fixed vendor and the MRP field can be 2 for both vendors to create schedule lines.
| | | ---------------Original Message--------------- From: jhemp2011 Sent: Tuesday, June 07, 2016 11:50 AM Subject: Dual Sourcing in SAP? I have a single part that we are ordering from 2 different suppliers. I have MEQ1 set up for a 70/30 split. MRP is not creating schedule Lines for the 2nd vendor. Both have separate scheduling agreements. Should the source list be fixed for both vendors? | | Reply to this email to post your response. __.____._ | In the Spotlight Become a blogger at Toolbox.com and share your expertise with the community. Start today. _.____.__ |