Hi pradeep,

Copy the old work schedule create a new record from 5th July in planned
working hours as 6hours. Then run the work schedule, it automatically give
as per date you have configured.

Regards,
Mamatha

---------------Original Message---------------
From: Pradeep Pai
Sent: Monday, June 06, 2016 7:17 AM
Subject: WSR Generation

Hi All,

We have one daily work schedule rule ( one which is without variant =
Planned working hours as 8 hours and one which is with variant = Planned
working hours as 6 hours)

We have generated WSR with daily work schedule rule ( as 8 hours) in system
But now now we want to generate WSR with daily work schedule rule ( as 6
hours) from specific date, This date is not the first date of the week , it
is in between week.

Eg : till 5th June WSR having planned working hours are 8 hours and now
wanted to generate WSR from 6th June till 4thJuly with planed working hours
as 6 hours.

Can you please let us know , How to generate WSR so that planned working
hours will be not 6 instead of 8 hours?

Thanks
Pradeep.

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
© 2016 Ziff Davis, LLC. and message author.
Ziff Davis, LLC. 28 E 28th Street New York, NY 10016
inscribeat  
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Become a blogger at Toolbox.com and share your expertise with the community. Start today.

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language