Question from anisha on Jan 10 at 6:24 AM partial GRN has been done against one line item of the PO, maintained header freight condition flagged grp condition, now when short closing this line item & creating new line item then balanced frgt charges is not getting distributed among existing line items. eg. grp condition Frgt at header 100 distributed as 50 & 50 line item 10 2 pc 100 (partial GRN of 1 qty) line item 20 2 pc 100 Now, short closing line item 10 & adding new line item 1 qty now value to be distributed as: line item 20 2 pc Rs. 50 line item 30 1 pc Rs. 25 instead it is distributing as: line item 20 2 pc Rs. 33.33 line item 30 1 pc Rs. 16.67 | Reply to this email to post your response. __.____._ | _.____.__ |