Re: [sap-log-mm] MRP Planning for Imported Material

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Reply from tilgulkarcn on Jan 8 at 11:57 PM
Hi,

First you need to define lead time in material master.

Second, it is your procurement department which need to spell lot size.

Third, initially you have to raise PO with manual requisition .

Next, after doing this also first two months system would warn you for the
shortages.

Thereafter your MRP cycle would give you results.

Enjoy the day.

---------------Original Message---------------
From: Saurabh
Sent: Wednesday, January 08, 2014 10:38 PM
Subject: MRP Planning for Imported Material

HI Experts,

My scenario is like we are getting the imported Material for our company after every 3 Months but here they are running the MRP every month .
So Please suggest how to plan for Imported Material through MRP .

Whether we should Plan for that Material i.e MRP TYPE PD or not .
Also tell me what lot size i should maintain along with Reorder Point .

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2014 Ziff Davis, Inc. and message author.
Ziff Davis, Inc. 28 E 28th Street New York, NY 10016
tilgulkarcn  
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Become a blogger at Toolbox.com and share your expertise with the community. Start today.

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language