Posted by anilsingh2710 on May 11 at 12:56 AM | Mark as helpful |
Hi,
I ahve checked for overall limit also , but it is allowing me to create the service entry for the same scenario.
I am going for a planned Service and need a check for the planned services as i am able to go for the service entry more than the PO Value. Is there any system message ,so that it checks the PO value and value of service entry and at next service gives an error if teh value get exceeded by the PO value.
---------------Original Message---------------
From: anilsingh2710
Sent: Monday, May 10, 2010 11:12 AM
Subject: PO Value
> Dear SAP Gurus,
>
> I have created a service PO of 15000 value and quantity 1 . created a service entry of 0.5 qty i.e of value 7500, then changed the PO to value 12500 for 1 quantity and then created service entry of remaining qty i.e 0.5 with value 6250. but if you see now value of PO is 12500 and service entry value is 13750, which is wrong. Is there any ways so that i can restrict the service entry so that it should not be greater than PO value.as quantity restriction is there as i cannot reduce the quantity once follow on document is created but value changed is allowed.
>
> Kindly help to resolve the above problem
__.____._ I ahve checked for overall limit also , but it is allowing me to create the service entry for the same scenario.
I am going for a planned Service and need a check for the planned services as i am able to go for the service entry more than the PO Value. Is there any system message ,so that it checks the PO value and value of service entry and at next service gives an error if teh value get exceeded by the PO value.
---------------Original Message---------------
From: anilsingh2710
Sent: Monday, May 10, 2010 11:12 AM
Subject: PO Value
> Dear SAP Gurus,
>
> I have created a service PO of 15000 value and quantity 1 . created a service entry of 0.5 qty i.e of value 7500, then changed the PO to value 12500 for 1 quantity and then created service entry of remaining qty i.e 0.5 with value 6250. but if you see now value of PO is 12500 and service entry value is 13750, which is wrong. Is there any ways so that i can restrict the service entry so that it should not be greater than PO value.as quantity restriction is there as i cannot reduce the quantity once follow on document is created but value changed is allowed.
>
> Kindly help to resolve the above problem
Copyright © 2010 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Related Content
In the Spotlight
_.____.__ White Papers
In the Spotlight
Your SAP Security is at Risk...Learn How to Stay Protected. Read the free white paper from SenSage