RE:[sap-log-mm] Capacity planning in production

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Posted by Joe_Kowalczyk
on Mar 15 at 4:10 PM
Mark this reply as helpfulMark as helpful
I had a typo should look like this..sorry

Labor
*
Operation quantity
/
Base quantity
/
No Employees ( which is the keyword from OPCY )

---------------Original Message---------------
From: Deepaknarain
Sent: Monday, March 08, 2010 11:24 PM
Subject: Capacity planning in production

> Dear all,
>
> I have the problem in the capacity planning and the result display on the MRP screen after creating the demand for the finished item.Here in our plant we have 10 forge machines in that we do multiple part nos in that forge cell the total capacity of that particular cell is to produce 45000 parts per day.We are producing the semifinished parts in the forge cell. In each forge machine 20 to 30 parts can be done in each machine.
>
> By creating the demand in the MD61 for the fert item the system plans accordingly for the child items based on the capacity.The problem is that the system is not giving me the correct demand for the plan it is generating the planned orders which is not meeting my daily demand of 45000 nos per day in that specific forge cell, instead it is generating 200 nos per day and another day of 10000 nos.