| | Posted by Tim Sykora (Lead ERP Business Analyst) on Mar 15 at 5:28 PM | |
I agree with Mr. McKay here ... MRP will choose the fixed vendor though. So if you want to really choose each time, in your source list, don't make either of them fixed. MRP will generate the requisition (or keyed directly it won't default). A buyer or buyer assistant will need to assign the source each time when creating the PO.
---------------Original Message---------------
From: DLT
Sent: Monday, March 15, 2010 12:59 AM
Subject: 2 Outline Agreements For Same Material
> We have a situation where one material is being purchased from 2 different vendors and we have Agreements in SAP with both vendors.
>
> What is happening is the system is not recognizing there are outline agreements for the material...and then release orders are not getting assigned. When we do a spend analysis of the agreement, the information is not accurate as release orders are not assigned. The system seems to be confused because there are 2 agreements and thus not able to "assign" and is not proposing/showing a choice between 2.
>
> What I am wondering is...is there a way to get the system to "propose' the 2 agreements when you are creating the release order...similar to when there is more than one "info record" and no agreement exists when creating a requisition...the system will show that there is more than one info record and you choose which vendor/material combination you prefer.
>
> Obviously there is similar functionality in "quota agreements" because the system will propose which vendor to order from based on % of spend etc. but you can choose which vendor on the quota arrangement to order from.
>
> From a "Business Process" viewpoint, one might ask why a company would have more than one agreement for the same material and the only explanation really is if the "material" is deemed strategic/critical to the organization and thus you want to ensure you maintain a relationship with more than one vendor incase your main vendor is short of supply/goes on strike/goes out of business etc...If you didn't maintain the relationship with another vendor and it is a critical material to your company...may cause a plant outages if you couldn't procure the material in a timely fashion! This is a key reason why you do quota arrangements...However, this is not the "scenario" for us and I am addressing this issue from a process perspective as well as SAP functionality to handle these situations.
__.____._ ---------------Original Message---------------
From: DLT
Sent: Monday, March 15, 2010 12:59 AM
Subject: 2 Outline Agreements For Same Material
> We have a situation where one material is being purchased from 2 different vendors and we have Agreements in SAP with both vendors.
>
> What is happening is the system is not recognizing there are outline agreements for the material...and then release orders are not getting assigned. When we do a spend analysis of the agreement, the information is not accurate as release orders are not assigned. The system seems to be confused because there are 2 agreements and thus not able to "assign" and is not proposing/showing a choice between 2.
>
> What I am wondering is...is there a way to get the system to "propose' the 2 agreements when you are creating the release order...similar to when there is more than one "info record" and no agreement exists when creating a requisition...the system will show that there is more than one info record and you choose which vendor/material combination you prefer.
>
> Obviously there is similar functionality in "quota agreements" because the system will propose which vendor to order from based on % of spend etc. but you can choose which vendor on the quota arrangement to order from.
>
> From a "Business Process" viewpoint, one might ask why a company would have more than one agreement for the same material and the only explanation really is if the "material" is deemed strategic/critical to the organization and thus you want to ensure you maintain a relationship with more than one vendor incase your main vendor is short of supply/goes on strike/goes out of business etc...If you didn't maintain the relationship with another vendor and it is a critical material to your company...may cause a plant outages if you couldn't procure the material in a timely fashion! This is a key reason why you do quota arrangements...However, this is not the "scenario" for us and I am addressing this issue from a process perspective as well as SAP functionality to handle these situations.
Copyright © 2010 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Related Content
In the Spotlight
White Papers
In the Spotlight
Earn Recognition for Your Contributions at Toolbox for IT. Gain Points for Community Achievements
View this thread online
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion