| | Posted by ha_tran (Senior SAP Supply Chain Business Analyst) on Feb 18 at 7:37 PM | |
Hi,
First of all, when running MRP via MD01/MD02/MD03 Transaction, it is the ''Create Purchase Requisition'' field setting which controls if purchase requisition or planned order will be generated. If it is set as ''1'', then the PR will be generated at all times and this will be the case if ''3'' is chosen. I guess your problem takes place when "2" was chosen in your system when running MRP. In this particular case, SAP will refer to the planning horizon to determine if PR or planned order will be created. If the requirement is within the planning horizon, then PR will be generated. Otherwise, it is the planned order which will be created.
Cheers,
HT
---------------Original Message---------------
From: peterpope
Sent: Thursday, February 18, 2010 6:50 PM
Subject: MRP/MPS Purchase Requisitions not always created
> Hello Gurus: We have situations when running MRP/MPS with setting to create purchase requisitions in opening period where on occassion a planned order is created instead of the expected purchase requisition. This issue occurs intermittently so it has not been easy to find the source of the problem. So, I have 2 questions: 1) any ideas why a planned order was created instead of the expected purchase requisition, and 2) can someone tell me the precise determining calculation MRP/MPS uses for creating a purchase requisition vs a planned order, using all the factors such as scheduling margin, GR days, Planned delivery time, opening period, procurement type, etc? Thank you in advance. Peter
__.____._ First of all, when running MRP via MD01/MD02/MD03 Transaction, it is the ''Create Purchase Requisition'' field setting which controls if purchase requisition or planned order will be generated. If it is set as ''1'', then the PR will be generated at all times and this will be the case if ''3'' is chosen. I guess your problem takes place when "2" was chosen in your system when running MRP. In this particular case, SAP will refer to the planning horizon to determine if PR or planned order will be created. If the requirement is within the planning horizon, then PR will be generated. Otherwise, it is the planned order which will be created.
Cheers,
HT
---------------Original Message---------------
From: peterpope
Sent: Thursday, February 18, 2010 6:50 PM
Subject: MRP/MPS Purchase Requisitions not always created
> Hello Gurus: We have situations when running MRP/MPS with setting to create purchase requisitions in opening period where on occassion a planned order is created instead of the expected purchase requisition. This issue occurs intermittently so it has not been easy to find the source of the problem. So, I have 2 questions: 1) any ideas why a planned order was created instead of the expected purchase requisition, and 2) can someone tell me the precise determining calculation MRP/MPS uses for creating a purchase requisition vs a planned order, using all the factors such as scheduling margin, GR days, Planned delivery time, opening period, procurement type, etc? Thank you in advance. Peter
Copyright © 2010 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Related Content
In the Spotlight
White Papers
In the Spotlight
Earn Recognition for Your Contributions at Toolbox for IT. Gain Points for Community Achievements
View this thread online
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion