Re: [sap-log-pp] Production version

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Posted by snadiminty
on Aug 10 at 12:20 PM
Mark this reply as helpfulMark as helpful
Hi Raj,
You need to have PV maintained in case of REM.
In discrete it can be optioned, but in REM it is must.
With the help of material, its product version - maintained BOM and routing
are got selected during backflushing i.e. while your production booking -
where you do you GI ( all components ). activity posting and GR ( of header
material)
Srini
On Mon, Aug 10, 2009 at 9:45 PM, Rob Pierce via sap-log-pp <
sap-log-pp@groups.ittoolbox.com> wrote:
> Posted by Rob Pierce(SAP Consultant, QA Testing Lead)
> on Aug 10 at 12:03 PM Raj,
>
>
> We use only one BOM, routing, etc for a material number and do not use
> PV for over 500,000 materials. You would want to use PV if your
> production is more flexible with long-term deviations or optional BOMs,
> routings, etc.
>
> Rob
>
>
> Rob Pierce
> SAP Consultant, SAP Project Support
> PACCAR ITD
> 425.254.6477
> ________________________________
> From: rrssap via sap-log-pp [mailto:sap-log-pp@Groups.ITtoolbox.com]
> Sent: Monday, August 10, 2009 3:22 AM
> To: Rob Pierce
> Subject: [sap-log-pp] Production version
>
>
>
> Posted by rrssap
> on Aug 10 at 6:23 AM
>
> HI Gurus,
> Doubt on PV...
> Is production version is mandatory master data? (either REM or Discreet)
> In REM is this essential to have PV?
> Thanks
> Raj