RE:[sap-log-pm] SAP PM sub orders
Posted by
Admin at
|
Share this post:
|
0 Comments
on 07/28/2009 01:29:00 PM
It sounds as though you need to use Budget Availability Control. This could be set at the fund, fund center or cost object level. I would recommend doing it at the fund center level. By using BAC you can define the process to issue warnings or hard errors at different stages of budget consumption. For example you may want a warning issued when 90% of the budget has been spent or committed and a hrd stop at 100%. By tying each sub order to a different fund center you would then get the control you needed.
Wendy __.____._
Copyright © 2009 CEB Toolbox, Inc. and message author.
Toolbox.com
4343 N. Scottsdale Road
Suite 280
Scottsdale, AZ 85251
Toolbox.com
4343 N. Scottsdale Road
Suite 280
Scottsdale, AZ 85251
View this post online
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion