Hi Basem,
Thanks for sharing.
This is also my question. I was able to perform the GR, however, I found out the SA without relase document type should be LP instead. I think the DATE and "display all item" in the personal setting are the key.
thanks very much.
Li
--- On Thu, 6/18/09, basem zedan via sap-log-mm <sap-log-mm@Groups.ITtoolbox.com> wrote:
From: basem zedan via sap-log-mm <sap-log-mm@Groups.ITtoolbox.com>
Subject: Re: [sap-log-mm] Scheduling agreement procedure
To: "ljkuoh" <ljkuoh@yahoo.com>
Date: Thursday, June 18, 2009, 2:27 AM
firstly after creating schedual agreement and maintain schedual delivery you can make goods receipt reference to purchase order , but you should notice that
1- make goods receipt at the delivery schedual date not before that because you will not contain any item , or you can also make goods receipt after the delivery schedual date
2-make schedual agreement type LPA (without release) not LP
3-try to do again and tell me what is the result.
regards
--- On Thu, 6/18/09, monika_laishram via sap-log-mm <sap-log-mm@Groups.ITtoolbox.com> wrote:
From: monika_laishram via sap-log-mm <sap-log-mm@Groups.ITtoolbox.com>
Subject: [sap-log-mm] Scheduling agreement procedure
To: "basem zedan" <bm_consultant@yahoo.com>
Date: Thursday, June 18, 2009, 7:15 AM
Hi all.
Could you provide me with the correct procedure for scheduling agreement?
I created a schedulin agreemt in me31L and then maintain the delivery schedule in me38. But when I am tryin to do the GR through MIGO_GR, it throws an error sayin the the document doesn't exist or no line items selected.
Am i following the correct procedure.
Please assist.
Regards,
Monika. __.____._
Toolbox.com
4343 N. Scottsdale Road
Suite 280
Scottsdale, AZ 85251
In the Spotlight
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion