Reply from VPSANKAR on Jan 17 at 4:55 PM Hi, Hope you are looking for some sort of notifications with respect to Budget control. If so, you can define the same in IMG. "Budget" - "Define Tolerance Limits". For example, Warning in case of Budget utilization @ 85% and Error Message in case of 100%. Thanks & Regards, P. Sankar
| | | ---------------Original Message--------------- From: Kamini Desai Sent: Wednesday, January 14, 2015 12:38 PM Subject: Soft Error When There is No Budget On the Specific WBS ELEMENT and the COST ELEMENT. Hi, I was wondering is there any way we can get the soft error when there is no budget on the specific WBS ELEMENT and the COST ELEMENT. | | Reply to this email to post your response. __.____._ | In the Spotlight Become a blogger at Toolbox.com and share your expertise with the community. Start today. _.____.__ |