Reply from Makal on Oct 20 at 10:28 AM Yes, you can use CN24N. Best Regards, Makal
| | | ---------------Original Message--------------- From: MarkMahoney Sent: Monday, October 20, 2014 6:48 AM Subject: Creating Operative Networks Without Sales Orders Good morning, We current plan our assembly processing using Sales orders, networks and WBS projects. In the future, we want to drop the need to raise Sales order, but still use networks and WBS projects to manage the configuration and planning dates for a 3 year horizon. We currently have circa 1000 sales orders live at any one time. If networks can be independant of sales orders, is there a way of managing them en mass? Thanking you in advance, Mark | | Reply to this email to post your response. __.____._ | _.____.__ |