Announcement:
wanna exchange links? contact me at sapchatroom@gmail.com.
Posted by
Admin at
Question from digiovannir on Sep 2 at 1:18 PM Hi all ! I would like to know if its possible to display cumulative processing % in network confirmation actual data screen. The scenario is this: Degree of processing is calculated by SAP when I confirm network activities/elements. 39% 05.07.2014 31.07.2014 72% 01.08.2014 31.08.2014 When I run transaction CN25 (or CJ20N) to enter a new network confirmation, I would like the system to display the cumulative processing (72%) I know I can use transaction CN48N to display network confirmations, however I would like to know what can I do to display the Pct in transaction CN25 Any suggest ? Regards, Rafael | Reply to this email to post your response. __.____._ | _.____.__ |