Announcement:
wanna exchange links? contact me at sapchatroom@gmail.com.
Posted by
Admin at
Toolbox sap-log-ps Question from digiovannir on Jun 10 at 4:54 PM Hi, I have an issue related to schedules dates in Milestone Trend Analysis When I run Milestone trend analysis report in PS, I use the chart options on the Graphic to select the "show value" option in Data label. To change the number format from standard value (i.e, 41881.612 to date 30-Aug-2014) I double click on the Milestone Marker and choose Date category to display the number in format dd-MM-yyyy I can see that the system displays the date in the Graphic as August 30th 2014, but when I follow the menu path Go to > Table, I realize that dates in the table are different
! ; I mean Schedule date in the table is September 1st, 2014 but in the graphic is Aug 30th 2014 When I analyze this values I found the the difference is two days earlier in all of the Milestones. Std. value Value converted Scheduled Dates in graphic to date format in table view ___________ ________________ ________________ 41960.612 17-Nov-14 19.11.14 41925.612 13-Oct-14 15.10.14 41881.612 30-Aug-14 01.09.14 41830.612 10-Jul-14 12.07.14 41798.288 8-Jun-14 10.06.14 Which could be the reason ? I will appreciate your help Rafael | Reply to this email to post your response. __.____._ | _.____.__ |