[sap-log-ps] Why schedules dates MTA table are different from dates in the Graphic?

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Toolbox sap-log-ps

Question from digiovannir on Jun 10 at 4:54 PM
Hi, I have an issue related to schedules dates in Milestone Trend Analysis

When I run Milestone trend analysis report in PS, I use the chart options on the Graphic to select the "show value" option in Data label.

To change the number format from standard value (i.e, 41881.612 to date 30-Aug-2014) I double click on the Milestone Marker and choose Date category to display the number in format dd-MM-yyyy

I can see that the system displays the date in the Graphic as August 30th 2014, but when I follow the menu path Go to > Table, I realize that dates in the table are different…! ; I mean Schedule date in the table is September 1st, 2014 but in the graphic is Aug 30th 2014

When I analyze this values I found the the difference is two days earlier in all of the Milestones.

Std. value Value converted Scheduled Dates
in graphic to date format in table view
___________ ________________ ________________
41960.612 17-Nov-14 19.11.14
41925.612 13-Oct-14 15.10.14
41881.612 30-Aug-14 01.09.14
41830.612 10-Jul-14 12.07.14
41798.288 8-Jun-14 10.06.14


Which could be the reason ?

I will appreciate your help

Rafael
 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2014 Ziff Davis, LLC. and message author.
Ziff Davis, LLC. 28 E 28th Street New York, NY 10016
digiovannir  

achievements
 
View this online
Ask a new question
 
In the Spotlight
Have a technical question? Need to find IT solutions? Ask your peers in the Toolbox for IT community.

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language