Question from Simon_Walter on Jun 5 at 4:11 AM
Hi Experts

When i try to do settlement to G\L account directly, it shows an error that "Settlement by cost element not possible due to secondary cost element"

In my project we some of the WBS need to be settled at a cost centre and some of the WBS need to be settled directly at G/L Account.

All the cost which needs to get settled against G/L account are not getting settled..

Any inputs will be highly appreciated

Thanks and Regards
Simon Walter
 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2012 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
pretty lady ask a question
 
Simon_Walter  

achievements
 
View this online
Ask a new question
 
In the Spotlight
Become a blogger at Toolbox.com and share your expertise with the community. Start today.

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language