Posted by Pramod Garg
on Apr 22 at 3:05 AM
Mark this reply as helpfulMark as helpful
Hi,

In SAP, KBK7 is normally used to actualized ending inventory value. If this
is the case, then Have you run CKMLCP to actualized ending inventory
balance?

Once it is run, MOH cost center is updadated with the actual MOH values.
Hope it will clarify


Pramod

On Thu, Apr 22, 2010 at 1:41 AM, mandyf via sap-acct <
sap-acct@groups.ittoolbox.com> wrote:

> Posted by mandyf
> on Apr 21 at 4:17 PM
> Hello, Can anyone help? I have run Splitting and Price Calculation which
> both give the results I expected, but although I get the mesage that the
> Price Calculation has posted, the sender and receiver cost centres are not
> debited and credited with the actualised values. This posting would clear
> the sender to zero. All the values are correct and the Actual Price for my
> activities is correctly updated in KBK7, as it should. Can anyone advise why
> the cost centres are not updated? Many Thanks for any advice Mandy
__.____._
Copyright © 2010 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
In the Spotlight
Did this response help you resolve your issue? Click the green 'Mark as helpful' arrow to vote on the entry.
_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language