Re: [sap-log-pp] Planned order scheduling
Posted by
Admin at
|
Share this post:
|
on 06/19/2009 12:03:00 AM
Dear Ranjeet
You are very right, but I am sure system definately doing the scheduling
based on some logic . You just check below mention parameters.
1. Check the start date of every plan order and found out where is the gap.
2. Wherever you found the gap check the resource load, may be non
availability of capacity system being re-schedule out the plan order.
3. Check the material availability / Lead time for Raw material being used
in B and C.
4. Check in the material master whether GR processing time has not maintain.
5..Check whether any float has not maintain.
Hope it should solved your problem.
If still not resolved pls revert back.
Regards
Vinod
On Thu, Jun 18, 2009 at 3:03 PM, Ranjeet via sap-log-pp <
sap-log-pp@groups.ittoolbox.com> wrote:
>
>
> Dear All,
> We have BOM for material "A" which consists of Sub-assembiles "B" & "C".
> The time required to manufacture "A" is 1 minute, "B" is 1 minute & "C" is
> 2 minutes.
> For a lot of 100 nos of "A", system generates one order of "A" with time
> requirement of 100 minutes, another order of "B" with time requirement of
> 100 minutes & order for "C" with time requirement of 200 minutes.
> Total put together, 3 orders requires 500 minutes, however as it is a
> continuous process, each quantity manufactured of "B" & "C" will be given
> for next process i.e. Assembly of "A".
> With this total time required will be 300 minutes instead of 500 minutes to
> complete the lot of 100 nos of "A".
> How this can be achieved?
> Thanks in advance for your help.
> Regards,
> Ranjeet __.____._
Toolbox.com
4343 N. Scottsdale Road
Suite 280
Scottsdale, AZ 85251
In the Spotlight
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion