RE:[sap-log-pp] Sub Contract PO and Stock Requirement List

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Reply from nalaj on Nov 19 at 7:15 PM
My question is, I have issued components to the purchase order using 541. Then the requirement for those components against the purchase order should be dropped. It should not appear in MD04 as requirement for that component. Otherwise, planner get confused . Why is not happening.

Why do we have to wait until the GR of the header material for the requirement of the component material to be dropped off?

Please suggest. It is kind of urgent.

Do I have to implement SAP Note ?1578969?

---------------Original Message---------------
From: Ram N
Sent: Friday, November 17, 2017 10:12 PM
Subject: Sub Contract PO and Stock Requirement List

Hi - I have created a sub contract PO. And Ran the MPR. It shows 2 entries in stock requirements list. I issued goods to the PO using movement type 541. And then Ran the MRP. I do not see any change to the stock requirements list.

Any idea what could be wrong?

Thanks

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
© 2017 Ziff Davis, LLC. and message author.
Ziff Davis, LLC. 28 E 28th Street New York, NY 10016
nalaj  
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Have a technical question? Need to find IT solutions? Ask your peers in the Toolbox for IT community.

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language