Announcement:
wanna exchange links? contact me at sapchatroom@gmail.com.
Posted by
Admin at
Question from kkestel on Sep 27 at 5:52 PM Hi SAP People! I have a bunch of things I'm ordering (boards, HLAs, etc) which have MOQs, but these MOQs can have the deliveries spread out over the course of 6 months as we need them. Is there a way to set the Material Master (or another spot) up so that we always order the MOQ, but spread out over that time period? I do not want 6 months worth of material at once, but I cannot order any less. I do not want to have to remember every single time (1000s of part numbers) that I need to break up the MOQ. Can SAP do this for me? Thanks! Kayla | Reply to this email to post your response. __.____._ | _.____.__ |