Hi

Why not try to create it as an installment payment term comprising two
lines ( 20 % and 80 % )? You can do this without specifying any days (
description furnished as 20 % payable as advance and 80 % payable based on
proof of dispatch of material ). This could split the entire document into
two line items ( 20 % and 80 % respectively ) and the first line item could
be utilized for releasing the advance payment ( any time you want to pay )
and the second line item for releasing the balance of 80 % once you are
convinced that the materials have been dispatched to you ).

Using Transaction Code OBB8, you could create two payment terms IN01 ( for
20 % ) and IN02 ( for 80 %) with descriptions as mentioned furnishing the
baseline date only ( usually , posting date ) and own description as
mentioned above.

Using Transaction Code OBB8, you could create one more payment term INST
wherein activate the installment payment term (it is a check box).

Using Transaction OBB9, you could capture two lines of payment term INST
with IN01 and IN02 furnishing 20% and 80% respectively.

Voila! Now you can use INST in your vendor master or vendor document and
the invoice splits itself into two line items and each line item can be
paid ( as per description ) any time you please.

Regards

VidhyaDhar

---------------Original Message---------------
From: ksuresh109
Sent: Friday, September 07, 2012 8:15 AM
Subject: Schedule the Payment According to the Payment Terms in PO

We have a problem with supplier payment term.
supplier payment term is 20% payment in advance, 80% after the material dispatch.
when we are looking to schedule the payment accordingly to the Payment terms in PO.
but while creating payment term we can give 20% adv with zero days, but for 80% payment after Dispatch of material we can not give exact days or date.
how can we schedule payment exactly.

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2012 Ziff Davis, Inc. and message author.
Ziff Davis, Inc. 28 E 28th Street New York, NY 10016
VidhyaDhar  
User-friendly SAP FI Consultant
18 achievements
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Have an SAP Question? Ask Your Peers at Toolbox for IT

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language