Question from Marcio on Aug 9 at 3:19 PM Hi, I have a problem with the "actual" cost component split, a value unjustifiable is presented in a cost element. I checked the cost elements assigned in OKTZ, and I can´t identify the reason for this value. In the processing of Material Ledger was not found problems. Our product is "configurable", then we have a cost element that indicates the finished materials used in the production of this material configurable. In this case, the element that is presented error is a cost element "variable." What I know about cost component split, a value in this element could only justified in case of exister in production order any "finish" product being counted in the cost element assignment in the OKTZ transaction. Could you help me please? Regards, Marcio Segundo | Reply to this email to post your response. __.____._ | _.____.__ |