Announcement:
wanna exchange links? contact me at sapchatroom@gmail.com.
Posted by
Admin at
Reply from Shinu on Jun 21 at 7:40 AM Hi, First you have to decide what is your baseline date? By default baseline date is = Document date. Now 25th of next month, is it Fixed,??? if it is Fixed , then u neeed to seek help from ababer to capture the base line date as per some conditions. Like, From Posting date identify the period, Add 1 to the period, (7+1 = 8) then start from the first day of the period till 25th. etc..... Regards Shinas
| | | ---------------Original Message--------------- From: Tidimo Sent: Thursday, June 21, 2012 7:06 AM Subject: New Payment Terms in OBB8 Hi expert, I need to create a new payment terms for vendor. My requirement is on 25 of the next month (follow month) with 3%, or 60d netto. What are the parameter i should insert in OBB8? Thanks | | Reply to this email to post your response. __.____._ | _.____.__ |