RE:[sap-log-pp] Routing master activity
Posted by
Admin at
|
Share this post:
|
0 Comments
| | Posted by cmghiorso (Applications Technologist) on Mar 23 at 5:11 PM | |
What settings do you have on your work centers on the routing? In CR02, work center maintenance, check the "Reference Indicator" check box for each activity type you have listed. I think this should help you.
With this setting checked, when you change a cost center activity type, master routings are updated automatically. And when you need to update an activity type in a order, clear the WC value on the operation (don't delete the whole operation) then re-enter the same WC value and hit enter. the new activity types should be pulled in.
---------------Original Message---------------
From: Deepaknarain
Sent: Monday, March 22, 2010 5:08 AM
Subject: Routing master activity
> Dear all,
>
> While creating the routing master i facing a problem in the operations tab after entering all the required fields like routing time for the man and the machine and specifying the workcentre etc is done but i am not getting the updation of the activity type in the intial screen for the man and the machine say 1201 and 1101 is not coming in the screen.But the case is different here the client i am working is the DEV client.
>
> Thanks in advance
> GSD
__.____._ With this setting checked, when you change a cost center activity type, master routings are updated automatically. And when you need to update an activity type in a order, clear the WC value on the operation (don't delete the whole operation) then re-enter the same WC value and hit enter. the new activity types should be pulled in.
---------------Original Message---------------
From: Deepaknarain
Sent: Monday, March 22, 2010 5:08 AM
Subject: Routing master activity
> Dear all,
>
> While creating the routing master i facing a problem in the operations tab after entering all the required fields like routing time for the man and the machine and specifying the workcentre etc is done but i am not getting the updation of the activity type in the intial screen for the man and the machine say 1201 and 1101 is not coming in the screen.But the case is different here the client i am working is the DEV client.
>
> Thanks in advance
> GSD
Copyright © 2010 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Related Content
In the Spotlight
White Papers
In the Spotlight
Earn Recognition for Your Contributions at Toolbox for IT. Gain Points for Community Achievements
View this thread online
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion