RE:[sap-log-mm] MRP schedule lines between two plants
Posted by
Admin at
|
Share this post:
|
0 Comments
| | Posted by ha_tran (Senior SAP Supply Chain Business Analyst) on Mar 23 at 7:55 PM | |
Hi,
By defining (via transaction OMD9) and assigning the special procurement key ''Stock Transfer from alternative plant'' (standard key 40) to your material item in Plant 4400 (Ordering Plant), any MRP run at Plant 4400 will generate automatically the stock transfer requisition to Issuing Plant (4200). Through the further setting of MRP Type via Transaction OMDQ where ''2'' is defined in the ''Include External Requirements'' field and the ''Purch. req. release'' indicator checkbox is flagged and assignment of this MRP Type to the material at the Issuing Plant (4200), another MRP run at 4200 Plant will take the schedule line of the stock transport requisition from 4400 Plant into account.
Cheers,
HT
---------------Original Message---------------
From: Deepaknarain
Sent: Tuesday, March 23, 2010 6:58 AM
Subject: MRP schedule lines between two plants
> Dear all,
>
> We have two plants ( 4400 ) is giving mrp generated schedule lines to other plant ( 4200 ). When MRP is run ( MDBT) by 4200 plant, schedule lines from 4400 should be taken as input. Benefits : Integration between 4400 & 4200, Time saving, better planning.
>
> kindly provide me some solution to have an integration.
>
> Thanks in advance,
> G.S.deepak
__.____._ By defining (via transaction OMD9) and assigning the special procurement key ''Stock Transfer from alternative plant'' (standard key 40) to your material item in Plant 4400 (Ordering Plant), any MRP run at Plant 4400 will generate automatically the stock transfer requisition to Issuing Plant (4200). Through the further setting of MRP Type via Transaction OMDQ where ''2'' is defined in the ''Include External Requirements'' field and the ''Purch. req. release'' indicator checkbox is flagged and assignment of this MRP Type to the material at the Issuing Plant (4200), another MRP run at 4200 Plant will take the schedule line of the stock transport requisition from 4400 Plant into account.
Cheers,
HT
---------------Original Message---------------
From: Deepaknarain
Sent: Tuesday, March 23, 2010 6:58 AM
Subject: MRP schedule lines between two plants
> Dear all,
>
> We have two plants ( 4400 ) is giving mrp generated schedule lines to other plant ( 4200 ). When MRP is run ( MDBT) by 4200 plant, schedule lines from 4400 should be taken as input. Benefits : Integration between 4400 & 4200, Time saving, better planning.
>
> kindly provide me some solution to have an integration.
>
> Thanks in advance,
> G.S.deepak
Copyright © 2010 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
SAP Logistics Material Management Helper
Posted helpful replies on 5 threads in a group to earn a Bronze Achievement
Related Content
In the Spotlight
White Papers
In the Spotlight
55% of IT Pros Use Social Media to Advance Their Careers. See the Survey Results
View this thread online
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion