| | Posted by kapil9507 (SAP SD Consultant) on Feb 15 at 2:30 AM | |
Dear all
my question is how to make the delivery from the sending plant??? lets not
only focus abt stock transport order. if i has happened in case of customer
sale and i have stock left in my godown and delivery challan shows 5 pieces
and customer has received 4 pieces. now he will do GR for 4 pieces. Now how
do i send the left out stock. I mean which document wud be used and with
reference to wat??
kapil
On Mon, Feb 15, 2010 at 11:45 AM, anshumanwahal via sap-log-mm <
sap-log-mm@groups.ittoolbox.com> wrote:
> Posted by anshumanwahal(consultant)
> on Feb 15 at 1:21 AM
>
>
> Receive the remaining one piece in your stock and post a subsequent return.
>
>
> Anshuman Wahal
>
>
>
> Date: Fri, 12 Feb 2010 18:53:12 -0800
> Subject: Re: [sap-log-mm] Short supply in stock transport order
> From: sap-log-mm@Groups.ITtoolbox.com
> To: wahalanshuman@hotmail.com
>
>
> Posted by ASST-MANAGER-LOGISTIC
> on Feb 12 at 10:08 PM
> Mark as helpful
> Hi,
> Balace 1 pc is siting in to Stock in transit (MB5T). As soon as the GR will
>
> be done for the 1pc,
> stock value will added to the receiving plant.
> Best regards,
> Achintya
> On 2/9/10, ha_tran via sap-log-mm <sap-log-mm@groups.ittoolbox.com> wrote:
>
> >
> > Posted by ha_tran(Senior SAP Supply Chain Business Analyst)
> > on Feb 10 at 2:57 AM
> > Hi,
> >
> > Sorry to say but i don't really get how the value of the fifth one is
> added
> > to the inventory value at Plant B if goods issue was only made for 4
> instead
> > of 5?. If goods issue is made for 4 pcs, then the stock quantity and
> value
> > of that material item at receiving plant will only increase by 4 and this
> is
> > logical.
> >
> > Cheers,
> > HT
> >
> > ---------------Original Message---------------
> > From: kapil9507
> > Sent: Wednesday, February 10, 2010 2:15 AM
> > Subject: Short supply in stock transport order
> >
> > > dear all<br/>my case is that i have created a sto from plant A to B for
> 5
> > quantities. Delivery is also created for 5. But the person who dispatched
>
> > the material by mistake loaded 4 materials, though the delivery challan
> is
> > for 5. the stock is lying in plant A. Now at the time of gr 4 materials
> are
> > detected and done the grn for 4. But the value of stock is transferred to
>
> > plant B at the time of delivery and the stock was in transit. now when we
>
> > have done the gr for 4, these materials are moved to main stock. but 1
> > material which is still there at the delivering plant, but value of that
> is
> > added to inventory in plant B. Now how do i reverse this 1 piece
> .<br/>thanx
> > in advance<br/>kapil
__.____._ my question is how to make the delivery from the sending plant??? lets not
only focus abt stock transport order. if i has happened in case of customer
sale and i have stock left in my godown and delivery challan shows 5 pieces
and customer has received 4 pieces. now he will do GR for 4 pieces. Now how
do i send the left out stock. I mean which document wud be used and with
reference to wat??
kapil
On Mon, Feb 15, 2010 at 11:45 AM, anshumanwahal via sap-log-mm <
sap-log-mm@groups.ittoolbox.com> wrote:
> Posted by anshumanwahal(consultant)
> on Feb 15 at 1:21 AM
>
>
> Receive the remaining one piece in your stock and post a subsequent return.
>
>
> Anshuman Wahal
>
>
>
> Date: Fri, 12 Feb 2010 18:53:12 -0800
> Subject: Re: [sap-log-mm] Short supply in stock transport order
> From: sap-log-mm@Groups.ITtoolbox.com
> To: wahalanshuman@hotmail.com
>
>
> Posted by ASST-MANAGER-LOGISTIC
> on Feb 12 at 10:08 PM
> Mark as helpful
> Hi,
> Balace 1 pc is siting in to Stock in transit (MB5T). As soon as the GR will
>
> be done for the 1pc,
> stock value will added to the receiving plant.
> Best regards,
> Achintya
> On 2/9/10, ha_tran via sap-log-mm <sap-log-mm@groups.ittoolbox.com> wrote:
>
> >
> > Posted by ha_tran(Senior SAP Supply Chain Business Analyst)
> > on Feb 10 at 2:57 AM
> > Hi,
> >
> > Sorry to say but i don't really get how the value of the fifth one is
> added
> > to the inventory value at Plant B if goods issue was only made for 4
> instead
> > of 5?. If goods issue is made for 4 pcs, then the stock quantity and
> value
> > of that material item at receiving plant will only increase by 4 and this
> is
> > logical.
> >
> > Cheers,
> > HT
> >
> > ---------------Original Message---------------
> > From: kapil9507
> > Sent: Wednesday, February 10, 2010 2:15 AM
> > Subject: Short supply in stock transport order
> >
> > > dear all<br/>my case is that i have created a sto from plant A to B for
> 5
> > quantities. Delivery is also created for 5. But the person who dispatched
>
> > the material by mistake loaded 4 materials, though the delivery challan
> is
> > for 5. the stock is lying in plant A. Now at the time of gr 4 materials
> are
> > detected and done the grn for 4. But the value of stock is transferred to
>
> > plant B at the time of delivery and the stock was in transit. now when we
>
> > have done the gr for 4, these materials are moved to main stock. but 1
> > material which is still there at the delivering plant, but value of that
> is
> > added to inventory in plant B. Now how do i reverse this 1 piece
> .<br/>thanx
> > in advance<br/>kapil
Copyright © 2010 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Related Content
In the Spotlight
White Papers
In the Spotlight
Earn Recognition for Your Contributions at Toolbox for IT. Gain Points for Community Achievements
View this thread online
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion