RE: [sap-log-mm] how to change contract PO?
Posted by
Admin at
|
Share this post:
|
0 Comments
| | Posted by Mr_Her (IT Support Manager) on Feb 15 at 11:07 PM | |
Ok, Tks. I've got it.
Another question, I saw a different validity date here, when clicking
'header details (F6)' it shows valid to 20-02-2010 however by clicking item
condition I can/may type 28-02-2010, which one will be used? ( I assumed
computer will use validity date in item condition, right?), what is the
header valid date used for?
Thanks.
Rgds,
Heryanto
_____
From: ha_tran via sap-log-mm [mailto:sap-log-mm@Groups.ITtoolbox.com]
Sent: 16 Februari 2010 10:38
To: Mr_Her
Subject: RE:[sap-log-mm] how to change contract PO?
Posted by ha_tran (Senior SAP
Supply Chain Business Analyst)
on Feb 15 at 10:39 PM
<http://it.toolbox.com/api/ContentVote/3308250/1/1/> Mark this reply as
helpfulMark as helpful
Hi,
When you are in ''Change contract: Item Overview'' screen, highlight your
related contract line item and click on "Item Conditions" icon (Shift F6)
(or you can click on Item ----> Conditions as well).
Cheers,
HT
---------------Original Message---------------
From: Mr_Her
Sent: Monday, February 15, 2010 9:05 PM
Subject: how to change contract PO?
> Dear all,<br/> <br/>I've created a contract PO using ME31K and saved it.
Now I wanna change the<br/>price in this PO using ME32K but its not possible
coz the price field is<br/>grey color. How to correct/change the price?<br/>
<br/>I need your help. tks<br/> <br/>Rgds,<br/> <br/>Heryanto<br/> <br/>
_____
__.____._ Another question, I saw a different validity date here, when clicking
'header details (F6)' it shows valid to 20-02-2010 however by clicking item
condition I can/may type 28-02-2010, which one will be used? ( I assumed
computer will use validity date in item condition, right?), what is the
header valid date used for?
Thanks.
Rgds,
Heryanto
_____
From: ha_tran via sap-log-mm [mailto:sap-log-mm@Groups.ITtoolbox.com]
Sent: 16 Februari 2010 10:38
To: Mr_Her
Subject: RE:[sap-log-mm] how to change contract PO?
Posted by ha_tran (Senior SAP
Supply Chain Business Analyst)
on Feb 15 at 10:39 PM
<http://it.toolbox.com/api/ContentVote/3308250/1/1/> Mark this reply as
helpfulMark as helpful
Hi,
When you are in ''Change contract: Item Overview'' screen, highlight your
related contract line item and click on "Item Conditions" icon (Shift F6)
(or you can click on Item ----> Conditions as well).
Cheers,
HT
---------------Original Message---------------
From: Mr_Her
Sent: Monday, February 15, 2010 9:05 PM
Subject: how to change contract PO?
> Dear all,<br/> <br/>I've created a contract PO using ME31K and saved it.
Now I wanna change the<br/>price in this PO using ME32K but its not possible
coz the price field is<br/>grey color. How to correct/change the price?<br/>
<br/>I need your help. tks<br/> <br/>Rgds,<br/> <br/>Heryanto<br/> <br/>
_____
Copyright © 2010 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Related Content
In the Spotlight
White Papers
In the Spotlight
Earn Recognition for Your Contributions at Toolbox for IT. Gain Points for Community Achievements
View this thread online
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion